Project Websites
I took advantage of an existing wiki technology available at Mortenson to create a standard template for project websites. These websites were used across the company to exchange nearly all project related information including the 3D BIM models and coordination…

Tulalip Hotel Integrated Work Plans
I generated integrated work plans for all concrete work throughout the 114,000 sqft first floor of the Tulalip Casino Hotel expansion project.

IDAT Disucssion Forum
While at Mortenson I instigated and supported the creation of an internal company discussion forum. This forum is now used to communicate and record lessons learned between team members, as well as track the value BIM has provided to projects.

Providence Everett Medical Center Civil Utilities Coordination
I modeled and coordinated the reroute of all underground utilities to make way for the new Providence Everett Medical center parking garage and hospital bed tower.

Everett Community Cancer Center MEP Coordination
I led the 3D MEP coordination process of the Everett Community Cancer Care Center using Navisworks Clash Detective. Additionally I was also responsible for modeling the pneumatic tube system using Autodesk Architectural Desktop.

Everett Community Cancer Center Tower Crane Erection
While working on the Everett Community Cancer Care Center project I used the 3D BIM model with the superintendent to plan the location and erection of the two tower cranes used by the project.

Fairview Research Center Business Development Structural Model
I used AutoDesk Architectural Desktop to create a business development structural concrete model. The image below shows the model overlayed with the architect’s SketchUp model.

Providence Everett Community Cancer Center Bed Tower 4D Model
Using Navisworks clash detective I created a 4D site logistics model of the Providence Everett bed tower project. This model was a key component to Mortenson being accepted for this $500 million hospital expansion.

Everett Community Cancer Center Site & Civil Coordination
While working on the Everett Community Cancer Center project I used the 3D BIM model with the project team to coordinate and plan the construction of underground utilities and footings. The pink line shown in the image above is a…

Everett Community Cancer Center Integrated Work Plans
I used the Everett Community Cancer Care Center BIM model to coordinate all embeds, formwork anchors, and block outs in the four building cores. The coordinated model was then used to generate a series of integrated work plans which were…